Water shows in Pull List when do staging

Dear Experts,

Presently, water are using in formula of mixing for bulk.

It is setting it as MRP Type "ND" - No planning. So, no purchasing requisition is triggered.

However, it is showing on Pull List every time to run even though water is no need to do staging in Pull List.

Please advise how to exclude water so that it will not be displayed in Pull List.

Thanks,

Phong

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Dec 13, 2016 at 11:42 AM

    Is your water inventory managed? How is it maintained in your bill of material?

    I think material requirements planning and planning material staging are 2 different things, and material staging does not look at a MRP type.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 13, 2016 at 03:42 PM

    Dear Jürgen L,

    Water is inventory managed and is in bill of material.

    Regards,