Dear Experts,
Presently, water are using in formula of mixing for bulk.
It is setting it as MRP Type "ND" - No planning. So, no purchasing requisition is triggered.
However, it is showing on Pull List every time to run even though water is no need to do staging in Pull List.
Please advise how to exclude water so that it will not be displayed in Pull List.
Thanks,
Phong
Is your water inventory managed? How is it maintained in your bill of material?
I think material requirements planning and planning material staging are 2 different things, and material staging does not look at a MRP type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jürgen L,
Water is inventory managed and is in bill of material.
Regards,
Phong
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.