on 03-23-2011 7:38 PM
how to upload forecast into sap.
Hi
You can use MD61 - create planned independent requirements or MM17 - Mass Maintenance
Thanks !
E.Avudaiappan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If by forecast you mean planned independent requirements, you can use BAPI_REQUIREMENTS_CREATE.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To import forecast values from a legacy system or another external system into the material master, use program RMPR1001.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.