Hi gurus,
I am trying to get the actual costs in a PM-order. Unfortunately not shown in the order.
PM-order was created with an equipment in the header.
PM order was released.
1 task has been confirmed with in TC IW41 with 5 h for this task.
The actual costs are not shown in the tab costs. Estimated costs, planned costs and actual costs show figures of 0.00. Actually there should be labour costs of 50.
The customizing settings for costing data for maintenance and service orders are already set up (hopefully all).