Former Member

CUT-OVER Strategy for SAP MM

Dear Experts

I was completing configuration of new company,Now i want to Uplaod the Cut-over data.

I want to know Cut-Over Strategy for MM.

Thanks

Sam

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 23, 2011 at 12:31 PM

    Hi,

    Firstly need to upload Master data such PIR, Source list Vendor master, Material master.

    You need to upload legacy open PO & Stock at plant location & vendor location.

    Then you need to upload Excise duties available in respective register if Plant is applicable to Excise.

    Rg

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 23, 2011 at 12:38 PM

    Chk the thread

    Cut over activities

    BR,

    Krishna

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 23, 2011 at 12:35 PM

    Hi There

    It is actually based on the Business,,

    Norammy following things will happen in Cut over activities,,

    1. Freezing the stock in Legacy

    2. Freezing the inventory movements/ transaction in legacy

    3. Org Structure/Plant/ P Organ assignments validation

    4. All Dev should be transported/All masters should be transported or created

    5. Batch Class and Characteristics creation in PRD system/ Batch Upload( If any)

    5. Inventory Upload and Validation

    6. Define release strategy in PRD system/ Check the User authorizations

    7. Any Z table update in PRD system directly

    8. Open PO/PR conversion if any

    9. If any transaction happend in Legacy which is not updated- Perform the same in SAP

    10. Send out the User ID and Pwd to users,,

    11. Set up the team, how the Go live support team will approach to the defects and Timeline for the tickets based on priority

    12. If any offshore/Onshore model define the same

    Note: Few of the customizations cant be transported from Dev to PRD, so we have to do it PRD system,,

    I may have missed some points here,, But these are all the steps are common in all type of businesses,,,

    Thanks

    Senthil