Hi,
I am facing a problem while downloading Project from SAP to MSP 2007 using openps version 4.03. What is happening is project data is getting copied, but the dates in SAP PS is not matching in the downloaded project in Microsoft project. I have maintained the factory calander in SAP and while downloading it is copied to MSP but it not considering the dates defined in SAP. note: in MSP always it is referening to standard base calander with 5 working days, where as my factory calander is defined for 7working days.
Need your assistance in this regards, how to match the factory calanders in MSP and SAP, aslo is the factory calander be different for different projects downloaded in MSP from SAP.
thanks
regards
kishore
Problem resolved by creating a new control key with setting as "schedule ext opr"
thanks kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Abdul Khader,
Thanks alot for your valuable answer, the notes attached really helped me out. I could able to over come the problem for some extent, manually when i cahnge the factory calander in MSP project wise problem is resolving, where as another issue i am facing is Once i do changes in MSP wrt to dates, while uploading project from MSP to SAP PS the new scheduled dates are not getting copied to the project in SAP, need your valuable advise in this regards also.
Thank you
regards
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please refer the below notes...
Note 857064
Note 579761
Note 656414
Note 656440
Note 534045
Note 534046
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.