Mar 23, 2011 at 11:48 AM

Downloading Project from SAP to MSP with open PS dates are not same

29 Views

Hi,

I am facing a problem while downloading Project from SAP to MSP 2007 using openps version 4.03. What is happening is project data is getting copied, but the dates in SAP PS is not matching in the downloaded project in Microsoft project. I have maintained the factory calander in SAP and while downloading it is copied to MSP but it not considering the dates defined in SAP. note: in MSP always it is referening to standard base calander with 5 working days, where as my factory calander is defined for 7working days.

Need your assistance in this regards, how to match the factory calanders in MSP and SAP, aslo is the factory calander be different for different projects downloaded in MSP from SAP.

thanks

regards

kishore