Alternative material maintenance for MRP run

241 Views

Scenario is below & expecting solution for the same.

1. Material "A" is having alternate material "B". Material A is maintained in simple BOM but material "B" is not maintained in BOM.

2. Both materials are material type "RAW".

3. In MRP, system generating planned order for material "A" and the same is converted into MRP PR.

4. But, for some reason ( Price and availability in local market ) client wants to prepare "MANUAL" PR for alternate material "B".

5. MRP strategy is "MAKE TO STOCK" & 40.

Questins are below.

1. i know that these manually prepared PR won't be calculated/considered for MRP qty towards SOP qty of our finished material.

Kindly expectign best solution for this.