Hi experts,

we are creating the auto pr from sales order for trading process with budget wbs element. but commitment is not posted in project wbs were as pr is created through sale order

pls suggest if any additional setting is required to post commitment while creating auto pr from sale order.

rgds

rajesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member214674
Contributor
0 Kudos

Check account assignement categories in SD for PR creation and See if you can make PR to be created with WBS as account assignement like we do in OPTT.