Hello Everyone..

While taking MRP run system is taking QM inspection lot stock also in account.

e.g..

if i am planning 1000 qty and have 50 inspection lot stock, then after taking MRP run it is generating planned order for 950 only.

We don't want to take quality inspection lot stock into consideration.

Suggest the configuration changes.

Accepted Solutions (0)

Answers (4)

Answers (4)

Anupam1143
Active Contributor
0 Kudos

HI

Following stock are taken into consideration for MRP:

1. Stock in Transfer

2. Blocked stock

3. Restricted use stock

those settings can be done from OPPQ or OPPI.

For your need you need to go another Sloc for QI stock and then Exclude this Sloc from MRP run thru T code OMIR with MRP indicator 1 and in MMSC with MRP indicator 1.

Regards

Anupam Sharma

former_member186193
Active Contributor
0 Kudos

hello,

can anyone will tell me if quality stock is taken into account for reservation.?

Alok

Former Member
0 Kudos

Hi,

one of the way to address is the problem is to have a QM storage location and deselct the storage location from MRP and it will not be consider for the planning.

Thanks,

JK

Former Member
0 Kudos

Hi,

one of the way to address is the problem is to have a QM storage location and deselct the storage location from MRP and it will not be consider for the planning.

Thanks,

JK

Former Member
0 Kudos

S/A,

OPPI. Deselect Restricted use stock.

Best Regards,

DB49

Former Member
0 Kudos

Hello DB,

We tried this setting already but it is not working for us.