We are on PPM 5.0.
I did the following (for Phase Approval)
- Specified DPR_APPROVAL_HIER as the approval document under "Phase Type"
- Under "Basic Settings > Forms for Printing and Project Status Reports> Activate ...", I activated the document under the relevant project type (both under "Print PDF form" and "Smart forms..." .
At the front end, I assigned the Decision Makers and carried out the required steps.
When I click on "Begin Approval", I get the following message:
"You cannot begin approval without an approval document".
Please advise.