on 03-16-2011 2:34 PM
Hi Team,
I am using MRP type as P1. And in the planning time fence, I am giving as 2. Can any one explain, how does the system will behave during MRP?
Thanks
Kumar
Hi,
MRP type P1: An order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed.
If you have maintained the planning time fence 2, then it means system will firm plan order during these planning time fence period.
Also check the below link,
[MRP|http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPMRP/PPMRP.pdf]
Thanks
Hrishi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Hrishi,
Thank you for the information. Can you please explain me with some example?
If i maintain the time fence as 1 what will happen and if i maintain the time fnce as 2 what will happen?
I could not able to open the link you have provided.
Please guide me. Your input will be appreciated very much.
Thanks
Kumar
Edited by: psk.psg on Mar 17, 2011 8:54 AM
Hi,
Planning time fence work on workdays, if you maintained 1 or 2 it means the 1 or 2 working days.
Order proposals that lie within a defined planning time fence (i.e.1 or2 in your case) are firmed for the planning run if
they are set to an MRP type with the appropriate firming type(i.e. P1 in your case). The firming indicator is not set and they are only firm as long as they lie within the planning time fence.
The link is in PDF format, hence might required more time to download.
[http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPMRP/PPMRP.pdf]
Thanks
Hrishi
Your required answer.
MRP Type P1 which firms our schedule agreement schedule lines at the end of the planning time fence
THe order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed
Firming : An order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed.
TQ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.