Hi Guru.

Im new. Im modeling APO DP. I created and actived the master plannig object structure. I created the planning area and the cvc manually (1 row). When i create the time series object the system says background job scheduled successfully and not planning version successfully initialized. Why? The status of the planning area is red. Thanks.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

i solved..the problem was that the planning version 000 was not consistent

Former Member
0 Kudos

Andreolli2,

How did you fix this problem?

Please hlp I am getting a simillar error.

I tried all the tricks mentioned in this thread its not working.

Thanks

Gayatri

Former Member
0 Kudos

Hi Andreolli2 ,

In your planning area go to tab Locking Logic and un checked Activate liveCache Lock and try to activate the planning area.

Regards,

Nikhil

aparna_ranganathan
Active Contributor
0 Kudos

Hi

Can you provide more details about the problem. Since you say that the planning area initialization status in red , it means the initialization job that you scheduled in the background ended with errors .

Check the job log and see what error message it shows. Based on the type of error message you can determine the course of action

Thanks

Aparna

Former Member
0 Kudos

there isnt an error code because the system says background job scheduled successfully but the status is red. culd be a problem about live cache?help me

aparna_ranganathan
Active Contributor
0 Kudos

No i think you did not understand what i said. Let me be more clear.

Go to transaction SM37 and display all the jobs that you scheduled in the background . The planning area initialization job will also show up . Now select that job and click on job log and you will be able to see the error. If you hav not used SM37 before take someone's help to do that

Thanks

Aparna

Former Member
0 Kudos

yes u right..maybe yhe error is livacache lock handler not available?

Former Member
0 Kudos

Now i have this error

Message test: Internal error [/SAPAPO/OM_TS_CHANGE_TG]

Message class: /SAPAPO/TSM/

Message number: 099

Message type: E

Plase help me

Former Member
0 Kudos

Hi Andreolli2,

looks like something wrong with the DB. Can you run the consistency check /SAPAPO/TS_LCM_CONS_CHECK and the DB check in OM17? After that make sure you activate the relevant MPOS before you initialize the planning area and also having at least one CVC is exists for the POS activation.

thanks!