What Date in CNS0 we need to enter in Planned Gds mvm tab under general dat

28 Views

Hi PS Guruu2019s,

Date should be after the (MRP2 tab in Material master Planned Delivery (Calendar day) + GR Processing Time (Working days))

Example:-

For materials A from Materials master days are two.

Thant means 16u2019Th March (consd'g 14'th march) we can enter data in CNS0 as in Planned Gds mvm tab under general data tab

Please correct me if I am wrong.

Many Thanks

MM