SAP UI5 Gantt Chart - Drag and Drop is not wokring

I developed Gantt chart based on SAPUI5 Explored Example: https://sapui5.hana.ondemand.com/explored.html#/sample/sap.gantt.sample.BasicGanttChart/preview.

It was working fine with all the functionalities like edit, drag and drop. But suddenly today Drag and drop is not working and by default the dates are updated to some wierd numbers like 1494809906272. Was there any recent updates or any logic is been changed?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 13, 2016 at 10:31 AM

    I found the solution. After drag and drop, the timestamp from event is in Epoch format. Just need to convert it in new date format.