SAP UI5 Gantt Chart - Drag and Drop is not wokring

Dec 12, 2016 at 01:46 PM

47

avatar image

I developed Gantt chart based on SAPUI5 Explored Example: https://sapui5.hana.ondemand.com/explored.html#/sample/sap.gantt.sample.BasicGanttChart/preview.

It was working fine with all the functionalities like edit, drag and drop. But suddenly today Drag and drop is not working and by default the dates are updated to some wierd numbers like 1494809906272. Was there any recent updates or any logic is been changed?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Betty Jebakumar Dec 13, 2016 at 10:31 AM
0

I found the solution. After drag and drop, the timestamp from event is in Epoch format. Just need to convert it in new date format.