how to create event trigger to kick off another report

Hi i am having two reports, first report runs for 10 minutes , i want the second report to run automatically after first report is completed. how to do that?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Mar 08, 2011 at 04:53 PM

    Create a schedule event in the CMC.

    Click Schedule on the report that needs to be triggered by the first report. Set recurrence and other options.

    Add the event to the "Events to wait for" list in the Events section.

    Schedule the first report to run, choose a recurrence and set needed options, and add the event to the "Events to trigger on completion" list in the events section.

    Admin guide also has a section on creating schedule events

    http://help.sap.com/businessobject/product_guides/boexir31/en/xi3-1_bip_admin_en.pdf

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Fritz Feltus

      Hi Fritz,

      I've created the schedule the same way you mentioned. ( Recurrence : Once with Start date - Today , End Date - some date in 2024).

      The schedule which waits for the event is in Pending state.

      I created the event for Success

      Thanks,

      Bharath

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.