Skip to Content
0
Mar 07, 2011 at 09:17 AM

Issue with Phantom Material in PCE

130 Views

Hi,

While creating the PCE for one of the finished materials, in the PCE, the phantom material is not getting selected.

There is no issue with the production version or BOM or Master recipe since in the process order after the BOM explosion the phantom material is being picked up.

The costing date of the PCE is also as per the production version validity date. In the BOM & master the phantom item is maintained for costing.

Let me know what else could be missing.

Thanks in advance,

Regards,

Abhijit