on 03-04-2011 11:01 AM
Hi All
Is it possible to add opearion to routing without base quantity?
I need to add operation to routing (painting which will take 5 days), which is not depeneded on quantity.
So its either 1 pc or 10 pcs in production order, this operation will still take 5 days.
Thanks
Best Regards
Andrey
This is controlled using a fixed formula in the parameter linked to work duration, i.e., not dependant on operation quantity.
But Operation quantity is a required field, because it is used also in confirmations, quantity of components, etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, I didnt realize that you will need a new WC.
But it the previous operations are quantity dependent and this is fixed, then it sounds reasonable that this can be done using a different WC.
Or check some of the operation times, for the last operation
(tear down, wait, move, )
to check if you can use one of them for covering the requirements.