on 03-04-2011 7:16 AM
Hi,
I am trying to create planning for product group, but getting error Factory calendar error (returncode = 3)
Message no. MA408
I have checked the validity for factory calendor but it is found ok with valid upto 2013. and allocation of factory calendor with plant 1000. the same factory calendor with validity is observed.
Pl help me out of this issue.
Regards,
Anil
Dear,
Please check have you maintained different factory calendars in the customizing for SOP (Transaction MC7F for S076) and for the plant OX10.
Please use same calendar in MC7F. and check again.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Check if you are using standard planning then for S076 in MC7F check factory calender is assigned is the same ehich is your plant or leav blank.
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.