Hi Experts,
Whenever we receive any material ( quality rejection from
plant A) at location X in film plant A, we can not do Transfer
posting of this material to crushing area ( location Y in plant A).
While doing Transfer posting we get an error " Pallet -
not consumed
entirely ".
We can not transfer this material to any other location.
What could be the problem?
Lokesh
Hi,
From the message it seems like in your system some message is activated. this might be due to the requirement was given that entire batch is to be consumed and partial is not allowed. please check this it should have been done through user exit or by some enhancement.