Std Cost Estimate

Former Member
0 Kudos

Hello Experts,

i am running a std cost estimate for a material..... system updated the current price in material master after CK11n. Now i added some more component in BOM of a header material.

when i again tryed to run the std cost estimate, system shows the error "Material STOOL_10" in plant 1000 has a released cost estimate"

Diagnosis

You are costing material STOOL_10" in plant 1000. This material has a released standard cost estimate for this period.

System Response

The material is not costed in this period because the current price in the material master record is linked to a released standard cost estimate.

I tryed CKR1 for deleting previous std cost estimate but it didn't work......... please help me in this regard.

- SAP PP

Accepted Solutions (0)

Answers (2)

Answers (2)

kiran_kumar179
Active Contributor
0 Kudos

Dear Delete the already created standard cost estimate in CKR1 transaction and re run the std cost estimate in CK11n or CK40n.

Cheers

KK

Anupam1143
Active Contributor
0 Kudos

Hi

You need to reorganise the cost estimate for the same material STOOL_10 in plant 1000 thru CKr1 for this period and also run without selecting test run check box in CKR1.

Regards

Anupam Sharma