on 03-03-2011 3:13 AM
Hi Friends
I hve a requiremnent to enhance the scheduing of the prod Order.
Currently Move time matrix is used to determine the Interoperation time.( ex. say 20 hrs between workcenter A to Work Center B)
Now we want to add/or subtract from this standard move time based on the charactersitic value (class type 001) for the Finished Product .
is there any enhancement spot /exit to adjust this time to a given logic.
Pls help to provide inputs
Thanks
Kk
Have you investigate the CAPP? It seem to be match with your requirement. The only difference is to maintain the characteristics value in routing instead of material.