Budget Checks in Classic for PO

Former Member
0 Kudos

Hi everyone,

We have a doubt with the budget checks in classic scenario and we need your help. We know when we create a SC, SRM verifies the budget in the ERP as a simulation. If there is not budget the system sends a error, but what happend with the PO?

For example:

Case 1: We create a SC. The SC is sent to SoCo. In SoCo, the strategic purchaser creates a bid invitation. A bidder wins the process and we whant to create a PO. When the budget is verified? The budget is checked before the PO is created in ECC or when? If there is not budget, the PO would not be created in ECC??

Case 2: We create a SC. The SC is sent to SoCo. In SoCo, the strategic purchaser assigns a contract then, he wants to create a PO. When the budget is verified? The budget is checked before the PO is created in ECC or when? If there is not budget, the PO would not be created in ECC??

We are working in SRM 7 with ECC 6 EhP 4.

BR

Ivá

Accepted Solutions (0)

Answers (2)

Answers (2)

yeushengteo
Advisor
Advisor
0 Kudos

Hi,

In classic deployment, commitment of budget only happens when the PR or PO follow-on documents are created in the ERP system. SRM SC has no capability to lock commitment in the ERP when the SC is released.

If you are looking at the commitment locking in the ERP when SC is released, you may like to look at the SRM PPS which has this capability in the extended classic deployment.

Regards.

YS

Former Member
0 Kudos

Hi Ranjan and Yeu Sheng,

About the SC, we have the same understanding.

Our doubt is about the PO. So, in the case when the PO doesn't have enough budget, the PO is created in ECC but is not released, is it?

BR,

Ivá

yeushengteo
Advisor
Advisor
0 Kudos

Hi,

I believe the PO will be in faulty status instead if E (message) is configured to alert budget insuficient when document is saved.

Regards.

YS

Former Member
0 Kudos

Hi,

The budget is vaidated when the XML message is processed in ECC. You can see the error message in TCODE SXMB_MONI.

Thanks,

Ivá

Former Member
0 Kudos

HI,

my understanding of budgeting says, the PO should be created in ECC backend system. But in case of insufficient budgeting, the PO should be sent for approval before being sent to supplier.

Thanks and regards,

Ranjan