Dear All,
I have partially confirmed one of internal activity. Details as below.
Normal Duration - 10 Days (which is maintained at internal activity scheduling sub screen)
Actual Duration - 4 Days (actual duration partially confirmed through tcode CN25)
Remaining Duration - 6 Days (This must be reflected in CN48N report as remaining duartion=Normal Duration - Actual Duration)
When i see CN48N report system dosen't show Remaining Duration as 6 Days, that field is showing as blank.
Why system is not updating remaining duration field in CN48N report. Any thing is missing from my side kindly give your valuable input.
Thanks & Regards
Sandeep