Hi

We are developing a process of Creation of Service Contract and then a order confirmation.

Now based on the Order Confirmation will bill based on the Bill Plan.

The Bill plan start date in contract header is not flowing to Sales Order header while creating with reference.

Then navigating to Header Billing plan and if we input the date the billing plan dates are displayed.

We checked the copy control settings and seems like the date is not copied.Is this a standard behaviour.

If so then do we have any work arounds to achieve the same. Because the contract start date can change before confirmation.

So business wants a sales order confirmation to be created after contract creation and bill periodically as per the Sales order instead of contract.