Dear Friends,
We are using SAP former budgeting system, we have an issue related to PO Budget.
PO created in the year 2009 and paid fully in 2010. no amount left to carryforward the PO to year 2011. As some additional amout need to pay against this PO value, user want to amend the PO.
To amend the PO, user has already created the PR in the year 2011 and when the user try to amend the PO using the newly created PR, getting the eoror message that budget exceeeded in the year 2009.
We want to know why the PO is refereing the Budget of 2009 and giving error message, even though we have sufficient budget in the year 2011.
Your usual support is greatly appreciated.
Regards,
Venkat