Hi Experts,
we have Existing release code 10,20,30,40,50 & 60. Now, we tried to add an intermediate Release Code(say 25) & release strategy(say R3) in existing release set up for PO.
And NO pre-requisite is defined ; final release by the last rel code.
However, the system shows release possible by 30 & 40 for last release strategy also. It`s showing the alternate release as release possible.
Pls throw some light on resolving the issue....
Regards,
Ganesh S....