Skip to Content
0
Former Member
Feb 25, 2011 at 12:55 PM

Planned cost not calculated in production order

1279 Views

Hello Costing Gurus,

i Have few production orders which are CTO orders and are collective orders.

The production created based on this is not showing the total plan cost when i go to production order - cost - analysis.

The production order is released.

The material is configurable and hence cant expect any cost estimate.

Question is :

1. What might be the reason the plan cost is not calculated or not showing?

2. What is the impact on the settlement or variance if planned cost is not calculated?

Can you please help.

Regards

Ananth