Hi Experts,

Need you help on below scenario of subcontracting returns.

I procure a material (X) from Vendor (A) in units of Meter, example rod. Later I send it to Vendor (B) for subcontracting (cutting) and get material (Y) in units of PC.

At the time of quality check of material Y, I observe cracks in the raw material supplied by vendor A and plan to return to him.

What would be your suggestion here, because I've to add up all the pieces to arrive to meters and return to Vendor A.

Example: 200 pcs x 0.21 meter = Total return is 42 meters.

Should I use a returns PO with material X OR returns PO with material Y and alternate UOM OR any other process which you think is better.

Please note this material is excisable

Thanks in advance

Rajoo