on 02-25-2011 7:30 AM
hi
We have a multi level BOM. We do the assembly in our workshop. When running MD4C we see we have exceptions in
lower levels. Is it a way to run a simulation without haveing to create alle the planned orders/requisitions for a planning purpose.
Hi,
You can use MD02 with simulation mode
In the simulation mode, results will not be saved to the data base directly.After checking the results in the simulation mode, we execute the planning run again if satisfied with the results.
regards,
sankaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi and thanks.
Maybe we have a problem in our client, but it seems to me that MD02 does not explode all levels when running, do you know anything about such a problem.
Also, when running in simulation mode, can this be downloaded? If we have a modell with a lot of items 500-1000 and
50-100 sub assemblies, it's time consuming doing this online.
Otherwise, you solved my problem