Hello,

A Purchase Requisition need to be created (for external services) at the time of Inspection lot generation. I tried using the Inspection Plan operation control key with 'Extenally processed processing' with Info record, Pur Org details.. etc. Still, when Inspection lot is released, Purchase requisition is not generated.

Any clue?

Thanks

JK

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Can you explain your business scenario.

In standard QM you cannot create purchase requisition from inspection lot creation.

1. You can use Userexit QAAT001 to create purchase req if needed.

2. Refer to "external processing in QM' if you want to create Purchase req during production.

http://help.sap.com/saphelp_46c/helpdata/en/42/75f1e256cc11d1896a0000e8323c4f/content.htm