Former Member

Purchase requisition to be created when Inspection lot is released

Hello,

A Purchase Requisition need to be created (for external services) at the time of Inspection lot generation. I tried using the Inspection Plan operation control key with 'Extenally processed processing' with Info record, Pur Org details.. etc. Still, when Inspection lot is released, Purchase requisition is not generated.

Any clue?

Thanks

JK

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 25, 2011 at 03:51 PM

    Can you explain your business scenario.

    In standard QM you cannot create purchase requisition from inspection lot creation.

    1. You can use Userexit QAAT001 to create purchase req if needed.

    2. Refer to "external processing in QM' if you want to create Purchase req during production.

    http://help.sap.com/saphelp_46c/helpdata/en/42/75f1e256cc11d1896a0000e8323c4f/content.htm