I saw many threads discussing scrap but none addresses this issue.
Lets say I have Prod Ord 1 to make Matl X for Qty of 10 with operations 10, 20 and 30. BOM has components A, B, and C with Qty of 10 each.
Now I am confirming operation 10 and scrapped 4 out of 10 and logged the same in Co11n.
I would think the system will generate a requirement for 4 additional A, B and Cs to meet the planned target of 10 X. So in total I would have consumed 14 A, B, and C to make 10 X's. Assuming no scrap in all other subsequent confirmations.
Is this correct. If yes what do I do to make this happen. i am not getting the same in my system.
It just doesnt plan any additional A,B or Cs.
thank you