Skip to Content

Material specification

Friends,

If I maintained already quality plan (QP01) of semi finished product with inspection type 04.

Is it necessary to maintain material specification by QS61 again with particular semi finished product?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 24, 2011 at 01:11 PM

    Material specification is not mandatory.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 25, 2011 at 05:19 AM

    Hi,

    It depends upon the inspection set up what you have maintained in QM view of the material master.(MM02)

    If you set indicator "Inspection with mat spec", you must maintain the material specification for the inspection to be performed.(QS61)

    If you set the indicator "inspection with task list" , the inspection is performed based on the task list(QP01)

    Hope your doubt is cleared

    Regards

    Hari

    Add comment
    10|10000 characters needed characters exceeded