Dear All

We are having no valuated WBS. We have Production Orders which are assigned with these WBS. Previously no planned cost are considered in WBS result analysis. But recently we found that in recently created production orders, system is considering the planned cost of production order in Result Analysis of WBS. In this case our material related costs get doubled as we also planned at WBS level for material cost..

Any idea what is the reason system is considering the planned cost of production order in WBS RA and how to restrict the same.

Thanks and Best Regards