Hi,
I have a planned order with Qty 50 (I have checked in MD16 it says qty:50)
Scenario 1:
I converted it to Purchase Requisition with qty.40, with change in qty. 10 numbers. After converting with qty. difference, I checked it in MD16, it say the qty as 10.
Scenario 2:
I converted it to Purchase Requisition with qty.60, with change in qty. 10 numbers. After converting with qty. difference, I checked it in MD16, I never find that Planned order in the list.
Now my questions are:
1. In which table this difference will be stored?
2. Or is there any t-code to see this Pl. order and PR qty. difference?
3. with respect to the second scenario why the planned order is not listed if i put more qty. in Purchase requisition than in the planned order?
4. Is there any setting to be done in IMG?
Thanks in advance.
Regards,
Dhan
9600934854
Edited by: DHANAVEL SUNDARAM on Feb 23, 2011 5:20 PM