GR for Scheduing agreement

Former Member
0 Kudos

Hi,

Can you please provide the detailed steps to do GR for SA with LP and LPA?

Transactions also

Thanks

Srini

Accepted Solutions (1)

Accepted Solutions (1)

former_member190537
Active Contributor
0 Kudos

Hello,

1) Create Scheduling agreement ME31L

2) Relese the Schdeuling agreement ME35L

3) Create Delivery schedule for SA ME38

4) Create goods receipt with reference to Scheduling agreement MIGO.

If JIT and Forcast Delivery schedules , then release JIT from ME84

Regards

Mahesh Naik.

Former Member
0 Kudos

In MIGO,i cant see the Scheduling agreement with referecne to the Goods receipt.

Former Member
0 Kudos

Hi,

In MIGO under PO tab you can give input as Schedule agreement no and press click

If you have schedule line then you can able to do GR to check schedule line go to ME38 enter the SA no Double click to see the Qty available for GR .

Rg

Answers (0)