Hello Friends,
We have a couple of issues with cProject Status "Completed" when ECC backend is still open for posting etc to get actual cost.
1. We have standard SAP program-DPR_EVE_BATCH_DPO running every night to update Project dashboard on cProject, which is not updating because of "completed" cProjects.
2. We have standard SAP program-DPR_CATS_CPR_TRANSF which pulls confirmation hours and remaining hours from ECC to cProject, fails due to cProject Status "Completed"
3. We have customized things which also fails due to cProject status "Completed" status.
So question is can we put any validation that ECC project should be set "CLSD" (closed) first with all settlements, cost gets zero balance and then cProject can be closed. The reason behind to keep first ECC closed and then allowing users to Complete cproject is we have control to close ECC project with error message if ECC project carries actual cost on it and ready to settle until it becomes zero balance.
Please suggest or advice if any thing we can do here.
Best Regards, Diana Charles.