Skip to Content
0
Former Member
Feb 22, 2011 at 02:55 PM

Forecast consumption in strategy 20

50 Views

Hi

We have strategy 40 in R/3 and 20 in APO. When we load PIR with VSF in R/3 , the forecast is allocated to STO PO and all other requirments in APO. We would like to use LSF in R/3 but the allocation in APO should happen only to SO , which is not happening now. Is there any setting missing?

Prasanna