Hi!
How to set it up?
I'm goíng to manufactor material A. To do that I will use B and C.
Now there is a change of plan. Material C has an alternative, material D.
Material B,C and D are of course also manufactored in "my plant" and
MRP relevant
There is plenty of C in stock, despite that, our construction department says that
material D is to have 100% probility in th BoM.
I want the system to use material C instead. In the PP-order it should read
e.g. 10pc of C and 0pc of D.
I want to set the system up so when C is below a certain stock level a planned order
is to be created to manufactor material D. No planned order is to be created for material C.
For material B planned order is created.
All of the requirements is originated from Sales-order.
Is this possible to set up with help of Discontinuation indicators and Probability?
This is probebly a piece of cake for you guys, but I'm rahter new at this.
I appreciate if you could take your time and help me.
Best Of regards Fredrik Wolf