on 02-22-2011 9:15 AM
Hi PM Exterts.,
Time confirmation of Operations is being done through IW41/IW42 by customer.
The customer enters the 'Actual Hrs' & 'Work ends on' date and the 'Work Start on' date/time is calculated based on this.
While listing the confirmations (from IW47), there are quite a few entries where the 'Work Start on' time is default (say 08:00:00).
What are the possibilities for this error (or) wrong calculation...? I tried to replicate the issue in QA, but it is working perfectly...
Kindly suggest.
Have you checked the config on execution of control parameters in IMG ? Does you dates and time are dfaulting in IW41 ?
Normally it should show up the same dates in IW47 as well.
Check the ocnfig and tables.
Mahee
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.