Hai Gurus,
I have one issue at my client place.
1) My cleint is a construction company, where we had implemented SAP PS, with
manual creation of PR/PO etc.
2) The current problem is while doing GI , the stores person had selected wrongly
the 'X' site( Plant) insted of 'Y" site( Plant) network and activity and done the GI
for the past two months, we came to know this problem only after defeciency
the allocated budget.
3) How to solve this problem, as GI is done for another plant network and activity
waiting for positive feed back.
Regards,
sekar chand.