HI ,

i am up grading my ECC ehp3 to EHP 4 , now i am in Java Phase , i got structed in this is phase . can any one help me ...

Software component sap.com/SAP_JTECHF with version 7.00.9.0 is found on the system but in the stack it is listed with version 7.00.0.0.

Software component sap.com/SAP-JEE with version 7.00.9.0 is found on the system but in the stack it is listed with version 7.00.0.0.

Software component sap.com/JLAUNCH is not found on the system but is present in the list of expected system components in the stack.

Thank s in ADVANCE ,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Select the option Find download files/select files manually and then Select "link to sp stack applications"

Select your source and target stack and then select the relevent kernel and stuff

and then go to cofirm your package , use the xml file which gets generated.

Make sure you move any existing xml files and use only the new one in EPS/in of the system where you are performing the EHP upgrade.

Gerard

sunny_pahuja2
Active Contributor
0 Kudos

>

> Select the option Find download files/select files manually and then Select "link to sp stack applications"

> Select your source and target stack and then select the relevent kernel and stuff

> and then go to cofirm your package , use the xml file which gets generated.

>

> Make sure you move any existing xml files and use only the new one in EPS/in of the system where you are performing the EHP upgrade.

>

> Gerard

He is doing dual stack upgrade of ECC system. So, stack xml file for service market place cannot be used.

Thanks

Sunny

Former Member
0 Kudos

Hi , Thanks for your replyes ,

i am not able to move forwarded with this step , i generated new xml file not possible it showing same error, so i did wt ever files it shown in Download Basket i deployed using JSPM , All deployed Success , now My java stack level is Latest level which shown in MOPZ. Now If continue the same step again it asking XMl file Stacak is not availbale

Now i dont want Upgarde Java Stck , hw can i move with ABAP upgrade for Next steps...

Can any one help me regarding this

Thanks in Advance

Kumar

Former Member
0 Kudos

Sunny,

I meant that we should intiialise the MOPZ and then select the "find download files" option from solman

that takes you to the SMP where you can select the source and target . it doesnt matter if its ABAP+Java

After downloading the files ,move them to the /usr/sap/trans of the server

Uncar all the .SAR and .sar files and they will automatically go into EPS/in

Move all the .SCA files and .xml file to EPS/in

Execute the EHP Installater it will automatically understand the Java and the ABAP part

Only one xml file is required.

Gerard

Former Member
0 Kudos

Try recreating your xml file and select only the ABAP components deselect all the SCA files in this case so that your xml doesnt contain the Java part . Hopefully you EHPi should understand that you want only the ABAP upgraded.

Former Member
0 Kudos

HI Gerarad,

Thanks for your reply ,

as you said tool need to understand only ABAP ,

i slect EPHI toll which is latest in SMP . in this I have 3 tab like Monitoring,ABAP,JAVA , i f select Lower verion should i get Only Monitoring,ABAP,.Can u help me which Version and patch level EPHi tools , this tool i selected SAPehpi_61-10005807.SAR.

Thanks In advance

Former Member
0 Kudos

Kumar ,

the problem is , the EHPi tool will sense that your system is a ABAP+Java system and will show up the Java tab as well.

SAP recommends upgrading ABAP and Java in synch. In your case since you have updated the Java support packages using SPAM. Try just selecting the ABAP components and create the xml file using MOPZ and use that in your EHP upgrade. Hopefully the tool will recognize that you need to have only the ABAP part upgraded since your xml contains only ABAP components .

Dont worry about the Java tab the tool should be in a postion to take care of it.

Let us know how it goes

Gerard

Former Member
0 Kudos

Hi Gerard,

Beginning i started with only ABAP(i didnt select my java system in Solman (SMSY) i chosse only ECC server not NW java as relevant ) then i processed ,so it not shown JAVA related Patches then i stated Upgrade it get completed then it came to J2EE then it saying No stack file. i am not able to Processed to next.

Thanks in Advance

sunny_pahuja2
Active Contributor
0 Kudos

>

> Sunny,

>

> I meant that we should intiialise the MOPZ and then select the "find download files" option from solman

> that takes you to the SMP where you can select the source and target . it doesnt matter if its ABAP+Java

>

> After downloading the files ,move them to the /usr/sap/trans of the server

>

> Uncar all the .SAR and .sar files and they will automatically go into EPS/in

>

> Move all the .SCA files and .xml file to EPS/in

>

> Execute the EHP Installater it will automatically understand the Java and the ABAP part

>

> Only one xml file is required.

>

> Gerard

You can do it for Netweaver system but you cannot do it for ECC system as you will not get ERP patches from SMP.

Thanks

Sunny

sunny_pahuja2
Active Contributor
0 Kudos

>

> Kumar ,

>

> the problem is , the EHPi tool will sense that your system is a ABAP+Java system and will show up the Java tab as well.

> SAP recommends upgrading ABAP and Java in synch. In your case since you have updated the Java support packages using SPAM. Try just selecting the ABAP components and create the xml file using MOPZ and use that in your EHP upgrade. Hopefully the tool will recognize that you need to have only the ABAP part upgraded since your xml contains only ABAP components .

> Dont worry about the Java tab the tool should be in a postion to take care of it.

> Let us know how it goes

>

> Gerard

If you want you can force EHPI tool to upgrade only ABAP part and leaving behind your Java part. Check SAP note 1245473. Please find extract from this note:

Dual-Stack Systems Only: Disabling the Java Stack Handling

If you have updated your ERP 6.0 system with EHP4 and later want to install further technical usages for the ABAP stack only, you can disable the Java stack handling. Do not use this option for any other purpose then the one stated above.

This option is available as of SAP EHP Installer 7.00 patch level 18. To disable the Java stack handling, start the installation program by entering the following additional parameter for executing the STARTUP script:

-srvarg=/DSUService/javadisabled=true

Thanks

Sunny

Former Member
0 Kudos

Sunny,

Good piece of information!

Gerard

Former Member
0 Kudos

Thank u sunny for info ,.

as you said i tried in SMP to download Ehpi toll which you mention , but with my Sno iam getting 7.00,7,10 ,in 7.00 only 64 patch available , SAP is not supporting lower version or removed form SMP .as you said java disable option is only for 18 patch , can u give some suggestion in this ,

iam strating tool like shoen bellow

EHPi>STARTUP.bat

then it

sdt/exe>DSUGui.bat.

Here where i need to give java disable option please can u mark here ,,

Thanks in Advance.

Former Member
0 Kudos

The option should work in patch 64 too. Remember its support "AS OF" 18 , meaning 18 and above.

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

As Gerard said, SAP Patches higher release always backward compatible. So, higher release contains the feature of lower release. So, you can use patch 64 and go ahead with your upgrade.

Thanks

Sunny

Former Member
0 Kudos

Hi Sunnay , Gerard,

i have started upgrade with your suggestion , it moving without JAVA Tab . now i got this Error while processing can you look into this

Insufficient free space in the database as follows:

Create TABLESPACE PSAPSR3701 with 7650

in my D drive i have 130 GB free space available , can u suggest me

Thanks

Former Member
0 Kudos

Kumar ,

You have to create the tablespace . Just go ahead and create it .

Its a new tablespace that you have to create

The logfile OTATAB.TXT contains the script to create them

Gerard

Former Member
0 Kudos

Hi,

Always found the dual stck upgrade through the EHpI a pain in the ass.

Run the Abap in through the EHpi and the Java in through JSPM do not use SDM you will get errors.

Mark

nirmal_konchada
Active Contributor
0 Kudos

Hi,

Check whether yu are using the correct xml file meant for the system.

Regards,

Nirmal.K

Former Member
0 Kudos

Yes nirmal .thanks for reply

this xml file generated using Solman Mopz..

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

I don't think so your stack file is correct as target release is lower than source release. Check your stack xml file.

Thanks

Sunny