Hi ,
I have created stock transfer requisition through CTM . but i am facing strange issue......
There is time difference between SNP: Purchase requisition(EA) and corresponding demand element SNP: Release for stk transp. requisition (EB) in other DC. As per my understanding there should not be any time diffence between receipt and corresponding demand element.
*There is no calander , handling , stotrage resource assigned in both the location.
No timestream assigned in TLane.
MY QUESTION is
1) why i am getting time difference between receipt and corresponding demand element.
2) There is no calander , storage, handling resource , no time stream in Tlane... in this case how scheduling happening?
regards
Rajesh.