Former Member
Feb 21, 2011 at 08:05 AM

mass strategy group change - 40 to 52

775 Views

Hi experts,

I want to change strategy group from 40 to 52 for about 2000 materials.

It implies that PIR type and customer reqmt type change from VSF/KSV to VSE/KSVS.

Mass PIR change is not a problem because PIR are transfered from an APO system.

But then there is an issue with existing schedule lines with customer reqmt type KSV which don't

consume anymore the PIR.

Is there a standard tcode or program to mass update the schedule lines rqmt type ?

What is the good practice to perform this change ?

Thanks in advance,

Raphael