I was needing a tracking report to check at least 3 months of changes to a project t code because I have to rectify it? This is my main problem The overall budget should be 2818 111 USD. the available balance for 2010 should have been carried over in 2011, however the overall showed 218 752 USD
Someone knows anything about it?
Thanks a lot
Hi,
As Abdul said, it is not exactly clear what you require.
CN60 is for change documents for a project.
For changes related to budget check CJI8 report.
Regards
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It is not clear from the post what exactly you are looking for.
CN60 is the tcode to check the change documents.
Tnx.
Abdul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.