Hi, All Experts!

I'm trying to implement next scenario in product cost planning:

1) The material has split valuation with two valuation type. Each valuation type has price S-3.

2) Cost estimate without quantity structure is created for the material. This cost estimate is created from non-SAP system. There is no valuation type as a criteria for creating cost est. without qty structure so the cost estimate is created for material only. This cost estimates is supposed to be the same for each valuation type.

3) I want to calculate and set standard price for each valuation type of the material. So I make a cost estimate with quantity structure which uses cost est. without qty str. as a reference variant. I want SAP to set the same price for each valuation type.

If I make no mixed costing for the material I get new standard price only at material (plant) level and only at one ("default in-house") valuation type.

If I make mixed costing with procurement alternative etc it can not update price in all valuation types too. I think it is happened because cost est. with quantity structure is using cost estimate without qty str as a reference.

Can I implement my scenario?

How can I update standard prices in all valuation types in material.

Can I extend cost estimate for some valuation type to other valuations types with some Z*?

Any useful things are welcome!