Hi

I need your help to resolve the below problem:

Requirement:

I am working on Planning for Process Industry and want to generate capacity based on the machine time, labour time and phase quantity used in production

What I did:

  • Created formulas parameter for machine and labor time

  • Created parameter for Phase qty (MGVRG field)

  • Created parameter for Base qty (BMSCH field)

  • Created formula for machine capacity: machine time * (phase qty / base qty)

  • In OPU5 and OPUZ I have enabled generate capacity and scheduling both in Detailed Req (with 04 as selection id)

  • In Resource the formula is giving the right value in test

Problem:

When I schedule the planned order after the MRP run, the Detail capacity and Rough-cut capacity tab appear, however in Detail capacity I ave Machine req: = 0 min and Labor req = 0 min. In Rough-cut capacity tab I dont get any row for the planned material.

Similarly on scheduling the planned order or process order the time taken is =0 min.

Also I couldn't trace the field MGVRG and SPLIM in the process order. Kindly let me know where can I find them.

Can any one please help to resolve this problem.

Thanks in advance

-Rahul

Edited by: khanna_rahul on Feb 17, 2011 6:30 PM