Hi
I need your help to resolve the below problem:
Requirement:
I am working on Planning for Process Industry and want to generate capacity based on the machine time, labour time and phase quantity used in production
What I did:
Created formulas parameter for machine and labor time
Created parameter for Phase qty (MGVRG field)
Created parameter for Base qty (BMSCH field)
Created formula for machine capacity: machine time * (phase qty / base qty)
In OPU5 and OPUZ I have enabled generate capacity and scheduling both in Detailed Req (with 04 as selection id)
In Resource the formula is giving the right value in test
Problem:
When I schedule the planned order after the MRP run, the Detail capacity and Rough-cut capacity tab appear, however in Detail capacity I ave Machine req: = 0 min and Labor req = 0 min. In Rough-cut capacity tab I dont get any row for the planned material.
Similarly on scheduling the planned order or process order the time taken is =0 min.
Also I couldn't trace the field MGVRG and SPLIM in the process order. Kindly let me know where can I find them.
Can any one please help to resolve this problem.
Thanks in advance
-Rahul
Edited by: khanna_rahul on Feb 17, 2011 6:30 PM