Strategy group 50

71 Views

Hello Every one,

In my current client I was planning to use strategy gorup 50 but I found some issues about which I was wondering whether anyone could provide clarity.

I am using strategy group for finished product (header material). I have given PIR Qtys for the same and when MRP is run system is automatically raising planned orders of order type LA. Which means the same can be converted to production order and I am able to convert the same.

But as I understand with strategy group 50, you can convert planned orders to production orders only if sales orders exist and

Dependent requirements for lower levels are thrown and can be manufactured but not header material.

So I am not sure why this is happening. Please do provide any inputs.

Sincerely,

Aji Kurian Mani