Hi All,
Can anyone throw light on how to change the legend in the network graphic for PS? For exmaple, is there a way to display partially confirmed activities in Yellow vs finally confirmed activities in Red?
HI,
Never tried but the config layout seems as if it is possible.
Follow the config path :
"sap netweaver - application server - front end services - network / hierarchy - define graphics profiles / node / links / colors etc.."
Standard graphics profile would be "PS - Network". Go to the "Node Group" list in that. (multiple selection icon).
try to find "PS_N_______1" group. Under this group you find number of color codes & form lines for each of the project objects (with their state).
Select activity part conf / fully conf & enter your required color there.
Pls share your experience on this, if you explore the above way.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.