Hi everyone,

Take the following scenario:

Workorder with material externally to be procured. Release WO, PR is created. PO is created with reference to PR and Goods Receipt is performed.

When setting the order now to status TECO, the PR item gets the status "Deleted" (field STATUSICON in the PR). This is strange because if looking at history you may think that the item was deleted. Howcome SAP does not use the field "Closed" (EBAKZ) in the PR?

We are using ECC 6 and as far as I can remember with 4.6 the functionality was different.

Anyone experience with this aspect or has asked SAP about this?