Hello Sir,
I am now working on easy cost planning tool. What I have seen is when I assign materials for cost planing in ECP tool , they get updated in S-ALR_87013532. We are doing this planning for reference.
But When we assign them under CJ20N for various movements, plannned cost gets updated twice. One because of ECP and one because of CJ20N.
So what to do ? Unit costing is better option in this case because S-ALR_87013532 doen't show planned value with CJ40 i.e. Unit costing method.
Girish